Part One IT Project Management
1 Approximately what percentage of the world’s gross domestic product is spent on projects?(b)
a.10 percent b. 25 percent c.50 percent d. 75 percent
2.Which of the following is a not a potential advantage of using good project management? (c)
a. Shorter development times
b. Higher worker morale
c. Lower cost of capital
d. Higher profit margins
3.A ____is a temporary endeavor undertaken to create a unique product,service,or result? (c)
a.program b.process c.project d.portfolio
4.Which of the following is not an attribute of a project? (d)
a.projects are unique
b.projects are developed using progressive elaboration
c.projects have a primary customer or sponsor
d.projects involve little uncertainty
5.Which of the following is not part of the triple constraint of project management? (c)
a.meeting scope goals
b.meeting time goals
c.meeting communications goals
d.meeting cost goals
6.______is the application of knowledge,skills,tools and techniques to project activities to meet
project requirement. (a)
a.Project management
b.Program management 项目组管理
c.Project portfolio management 项目组合管理
d.Requirements management
在项目组合管理中,组织将项目以及项目群组合并进行管理,使其作为一个投资组合,从而促成整个企业的成功。
项目群是指"一组相互联系的项目,宜使用协同方法进行管理来获得收益和进行控制,而这
种收益和控制在单独管理这些项目时是不易获得的"。
7.Project portfolio management addresses _______ goals of an organization ,while project
management addresses _______goals.(a)
a.strategic(战略),tactical(战术)
b. tactical(战术), strategic(战略)
c.internal,external
d.external,internal
8.Several application development projects done for the same functional group might best be
managed as part of a _____.(b)
a. portfolio b. program 项目群 c.investment d.collabortive
9.Which of the following is not one of the top ten skills or competencies of an effective project
manager?(d)
a. people skills b. leadership c. Intergrity 正直 d. technical skills
10.What is the certification program called that the Project Management Institute provides?(b)
a.Certified Project Manager(CPM)
b.Project Mangement Professional(PMP)
c.Project Management Expert(PME)
d.Project Management Mentor(PMM)
Part Two The Project Management and Information Technology Context
1. Which of the following is not
part of the three-sphere model
for systems management?(b)
a.business b.information
c.technology
d.organization
2. Which of the four frames of organization addresses how meetings are run,employee dress
codes,and expected work hours?(d)
a.strutural b.human resources c.political d.symbolic 标志
3. Personnel 人 员 in a______organizational
structure often report to two or more bosses.(c)
a.functional b.project c.matrix
d.hybird
4. Project work is most successful in an organizational culture where all of the following
characteristics are high except______.(d)
a.member identity b.group emphasis c.risk tolerance d.control
(1)成员认同:雇员将组织当做一个整体加以认同的程度,而不仅仅是认同他们的工作或职业类型。
(2) 强调群体:工作活动是围绕群体或团队,而不是个人开展的。强调群体工作的组织文化有利于管理项目。
(3) 关注员工:在何种程度上管理层的决策考虑到其成果对组织中人员的影响。
(4) 单位整合:在何种程度上组织鼓励各个单位或部门彼此协调整合。
(5) 控制:规定、政策和直接监督在何种程度上用于监督和控制员工的行为。
(6) 风险容忍:在何种程度上组织鼓励员工进取、创新和敢冒风险。
(7) 奖励标准:奖励,例如升职和加薪,在何种程度上取决于员工的表现而不是资历、偏爱或其他非绩效因素。
(8) 冲突容忍:在何种程度上组织鼓励员工公开地摆明冲突和进行批评。
(9) 过程一结果导向:在何种程度上管理层关注结果而不是达到结果的技巧和过程。
( 10) 基于开放的系统:组织多大程度上监视外部环境的变化并对其作出反应。
5. A_____is a product or service,such as a technical report,a training session,or
hardware,producted or provided as part of a project.(a)
a.deliverable b.product c.work package d.tangible goal 切实目标
6. Which of the following is not a phase of the traditional project life cycle?(a)
a.systems analysis b. concept c.development d. implementation
project life cycle:项目生命周期就是一系列项目阶段的集合。通常项目生命周期定义了每个阶段需要进行的工作、产出可
支付的成果、何时产出和各个阶段所需的人员。
4 个阶段:定义、开发、实施和收尾。
7. What is the term used to describe a framework of the phases involved in developing
information systems?(a)
a. systems development life cycle
b. rapid application development
c. predictive life cycle
d. extreme programming
8. Another name for phase exit is a_____point.(d)
a.review b.stage c.meeting d.kill
9. The nature of information technology projects is different from projects in many other
industries because they are very_____.(c)
a.expensive b.technical c.diverse(多样的,变化多的) d.challenging
10. What term is used to describe when an organization acquires goods and/or sources from an
ouside source in another country?(b)
a.globalization b.offshoring(离岸外包) c.exporting d.global sourcing
Part Three Project Management Process Groups: A Case Study
1. A_____is a series of actions directed toward a particular result.(b)
a.goal b.process c.plan d.project
过程(process),是针对某一特定结果的一系列行动。项目管理过程组(project management process groups) 包括启动活动、计划
活动、实施活动、监控活动以及收尾活动。启动过程(initiating proceses) 包括定义和授权一个项目或项目阶段。
2._______processes include coordinating 协调 people and other resources to carry out 实施 the
project plans and produce the products,services,or result of the project or phase.(c)
a.Initiating b.Planning c.Executing d.Monitoring and controlling e.Closing
计划过程(planning processes),包括设计并维护一个切实可行的计划,以确保项目专注于组织的需要.
实施过程(exeutingprocesses) ,包括协调人员和其他资源,实施项目计划,产生项目产品、服务、项目结果或项目的阶段结果。
监控过程(monitoringand controlling processes) ,包括定期测量和检查项目进程以确保项目团队能够实现项目的目标。
收尾终止过程(closing processes) ,是对项目或者项目阶段的正式接收,并使之高效率地收尾。这一过程组往往包括一些行政管
理活动,如归档项目档案、终止合同、总结经验教训、对项目或项目阶段进行正式验收等。
3.Which process group normally requires the most resources and time?(c)
a.Initiating b.Planning c.Executing d.Monitoring and controlling e.Closing
4.What methodology was developed in the U.K.,defines 45 separate subprocesses,and organizes
these into eight process groups?(d)
a.Six Sigma b.RUP c.PMBOK Guide d.PRINCE2
PRINCE 是 PRoject IN Controlled Environment(受控环境下的项目管理)的简称。
5.Which of the following outputs is often completed before initiating a project?(b)
a.stakeholder register b. business case c.project charter d.kick-off meeting 开工会议
6.A work breakdown structure,project schedule,and cost estimates are outputs of
the_____process.(b)
a.Initiating b.Planning c.Executing d.Monitoring and controlling e.Closing
7.Initiating involves developing a
project charter,which is part of the
project______management knowledge
area.(a)
a.intergration b.scope
c.communication d.risk
计划和监控在所有管理中都存在,启动只有在项目集成管理中出现
8.______involves measuring progress toward project objectives and taking corrective action.(d)
a.Initiating b.Planning c.Executing d.Monitoring and controlling e.Closing
9.What type of report do project teams create to reflect on what went right and what went wrong
with the project?(a)
a.lessons-learned report 经验总结报告
b.progress report
c.final project report
d.business case
10.Many people use______to have a standard format for preparing various project management
docunments.(b)
A.methodologies 方法 b.templates 模板 c.project management software d.standards
Part Four Project Integration Management
1. Which of the following processes is not part of project integration management?(a)
a. develop the project business case
b. develop the project charter
c. develop the project management plan
d. close the project or phase
2. What is the last step in the four-stage
planning process for selecting information
technology projects?(d)
a. information technology strategy
planning
b. business area analysis
c. mind mapping
d. resource allocation 资源分配
剩余23页未读,继续阅读
SLHJ-Translator
- 粉丝: 27
- 资源: 297
上传资源 快速赚钱
- 我的内容管理 展开
- 我的资源 快来上传第一个资源
- 我的收益 登录查看自己的收益
- 我的积分 登录查看自己的积分
- 我的C币 登录后查看C币余额
- 我的收藏
- 我的下载
- 下载帮助
安全验证
文档复制为VIP权益,开通VIP直接复制
信息提交成功
评论0