第一部分
一、客观题
1
:
The first step in project planning is to
A) determine the budget.
B) select a team organizational model.
C) determine the project constraints.
D) establish the objectives and scope.
2
:
Which of these software characteristics is not a factor contributing to project coordination
difficulties?
A) interoperability
B) performance
C) scale
D) uncertainty
3
:
Which of the following is not generally considered a player in the software process?
A) customers
B) end-users
C) project managers
D) sales people
4
:
The best project team organizational model to use when tackling extremely complex
problems is the
A) closed paradigm
B) open paradigm
C) random paradigm
D) synchronous paradigm
5
:
Small agile teams have no place in modern software development.
A) True
B) False
6
:
Which of these are critical practices for performance-based project management?
A) assessing product usability
B) defect tracking against quality targets
C) empirical cost estimation
D) formal risk management
E) b, c, and d
7
:
Effective software project management focuses on four P's which are
A) people, performance, payoff, product
B) people, product, performance, process
C) people, product, process, project
D) people, process, payoff, product
8
:
The major areas of problem decomposition during the project scoping activity are the
A) customer workflow
B) functionality to be delivered
C) process used to deliver functionality