C1.1 CASE STUDY
Case Study of “The GPS Auto-navigation System Verification Project”
NAME:XUANMING LIU
ID:3180106071
SUBMIT DATE:2020.12.10
Case Study of “The GPS Auto-navigation System Verification Project”
Requirement 1: Project Organization
(a) develop an initial project charter
Project number
20201205
Project name
The GPS Auto-navigation System Verification Project
Project background
An external product audit had been conducted by
randomly selecting three of the 15 prototypes for a
“tear down” audit inspection. The inspection had been
completed and there were some discrepancies in the
audit, ranging from engineering design issues to
workmanship.
Project propose
5 systems would receive a “tear down” workmanship
assessment and engineering design review to
determine any product/manufacturing implications of
defects identified in the workmanship review. The
purpose of this operation is to prove that IRIS was a
great system, capable of exceeding all field
expectations for reliability.
Project manager
Xuanming LIU, The Manager of Reliability Engineering
Project member
1. Gail YU, Manager of Quality Engineering
2. Tom HUANG, Manager of Design and Product
Engineering
3. Jesse LIU, a senior engineer from Product
Manufacturing
4. Pete DONG, a senior engineer from
Administration responsible for component
purchasing and incoming testing of materials.
Scope
We need to finish this test project as soon as possible,
Case Study of “The GPS Auto-navigation System Verification Project”
including tasks listed below:
(1) developing the project plan and schedule
(2) conducting the reliability testing of the guidance
systems,
(3) conducting the tear down audit and interpreting the
results
(4) reporting the results of the project to Senior
Management.
task
Deadline
a briefing in one week
concerning your plan for
the reliability testing
end of first week
meeting to develop the
company position and
strategy
end of second week
Primary tests result
end of second week
a full customer briefing
end of third week
Time schedule
Finish the tests
end of third week
(b) develop a complete Linear Responsibility Chart
Key
1-responsibility,
2-supervision,
3-must be consulted,
4-may be consulted,
5-must be notified,
6-approval authority.
剩余13页未读,继续阅读
曹将
- 粉丝: 20
- 资源: 308
上传资源 快速赚钱
- 我的内容管理 展开
- 我的资源 快来上传第一个资源
- 我的收益 登录查看自己的收益
- 我的积分 登录查看自己的积分
- 我的C币 登录后查看C币余额
- 我的收藏
- 我的下载
- 下载帮助
最新资源
- TG-2024-05-23-204718255.mp4
- 候志强@181 5428 8938_20240420112107.amr
- spispispispispi
- 实验二:IP协议分析.zip
- 驱动代码驱动代码驱动代码驱动代码
- SVID_20240523_141155_1.mp4
- Code for the complete guide to tkinter tutorial
- 关于百货中心供应链管理系统.zip
- SimpleFolderIcon-master 修改Unity的Project下的文件夹图标
- A python Tkinter widget to display tile based maps
资源上传下载、课程学习等过程中有任何疑问或建议,欢迎提出宝贵意见哦~我们会及时处理!
点击此处反馈
安全验证
文档复制为VIP权益,开通VIP直接复制
信息提交成功
评论0