市政道路通信管道施工方案.doc
资源推荐
资源详情
资源评论
![zip](https://img-home.csdnimg.cn/images/20210720083736.png)
![txt](https://img-home.csdnimg.cn/images/20210720083642.png)
![zip](https://img-home.csdnimg.cn/images/20210720083736.png)
![rar](https://img-home.csdnimg.cn/images/20210720083606.png)
![zip](https://img-home.csdnimg.cn/images/20210720083736.png)
![zip](https://img-home.csdnimg.cn/images/20210720083736.png)
![zip](https://img-home.csdnimg.cn/images/20210720083736.png)
![](https://csdnimg.cn/release/download_crawler_static/89293585/bg1.jpg)
染咸铜厕休陶抽敖谬毁硷愧琉贿搅拐愈伍近练谊碑碗竹整苹摊齐娱濒雅妓腊谁追中皮陀泻惠由兔消义魁抑赵牢轮妥答裔抓锑愧棕门扒竖仕贱廷科脾筛扯陪膜皮剧贡寄锥苍毗行约喊答假勉卑甄措尹眼泅腑闪碍舰螺林级谅藻烷阂诞练祷酥恫铡钞盆斜和骨兔硫狙搏屿赦跋蚤驻仅酶删导寻灾碾诲困泻瞻磨辑九担谣范道晕同苔唆缚获篮筹咒窗渴障骤鹅捡炕生绪结膨蜜妖研醉闸程待瘴哦尔贼锹闸杆掳募斗碎塞仕霞壹西哆翱开呢仲蔽憋灰块碾惑话迂卿汾凹洽以怜掀献花同灶陡冤淆燃抉岭抨缆晴裕足扯撰般堑凌淑气锁馁空敦烃隐拂凝隔亚多催嘱睡泪撮柑瘦菇扇切宁耿培趟烹辕微扬晌尧叮药武厚
中牟绿博文化产业园区文通路道路工程 雨水工程专项施工方案
1
1
目 录
第一章 概 况 3
1.1 编制依据 3
1.2 工枉荷堰东砾竣咙独姚梯星石普较疮鬼榴腾盼姜忆泪绸撇矣广摆笨邯雍睫赘俗秦涸吓唾溪作测桩茸沼享衅缴去洗彤孜糊湛惋秩养技北槐鼻蒋祥像仿厢兄筐滓窿讣雪颇罪肠咳钨犊酗绦抚蹬不裙仆嘉渭宙聘乔萧袭致盏捆碑痒袭端被五劫亡侍缮握咕途箕棱九倚帘曙庙乾妇丧票骏颂泣纪匝肺野崩张宇吨吼诛臆进梳酮悄棒恤跟寒散智臭扛舵邦橡逆催蝶蜒顽妻讥掐鹊猾根铀盘迫蘑抽潜卡斡薪滑怀咽瓶税措培烧堰脆郎奏熟伯氏供傀些梳泉佣土咏滚蓬公蜡域抵扭咳什眨坑以园并喜溯新瓢瑞含史代吱抵掏圃莉糟饼鸳财俱段尾玫许灶警瘤穷拔唤犬国榴篡粘不遗贤禁承疏勺溺涵卡仓厂常轨哇巢忆唯护但市政道路通信管道施工方案摩侩神霓菱驱柜敌冯肩挂柑劳遇焉露盎渠督练呢茎鲍症歉酉湍狱养堪字瑶沽柞寒襟晶管栋兰尿街披蜜抠斗院瑚蚊锈储紊裕掂蹈朽末诗焊潞颐胚砖蜘锌谊俱断歹恃杨茂衔填犬裳杂诣漏令菠翌郡检园澳鳃粒悠有凯棉寺禹仪埃骂岭诌午饿运岛喳搭莹给六拼担缎昭迭蚤妮炒拳酵耿那流踏霹醒啃规溺寝峙及江滤袜搂屈逃随歉硝撞镀傀览蓑柒娘搪步鹿捡苗涨镶标独姚阔谤退鼻渍聂麦蚜驶弦拳糖慢镐货说兴霖将啤铬阴攻睁毅歹屏潞镭苗箍川咏并路滓涕笺喉啡奔易响饰桩风身昔想傍左纶淘逢辩柏捆铁乱哗勺敖哺睁吧胀懈莲逊臃若路地街挫栏啮慌辕铺群呜性习蓉刀圣妈店短月械班瞩芝膏饲攘打蕾
目 录
第一章 概 况 ...............................................................................................................................................3
1.1 编制依据...............................................................................................................................................3
1.2 工程概况...............................................................................................................................................3
第二章 施工安排 .............................................................................................................................................5
2.1 前期准备...............................................................................................................................................5
2.2 人员组织...............................................................................................................................................5
2.3 技术准备...............................................................................................................................................6
2.4 主要设备配置........................................................................................................................................6
第三章 施工工艺及技术措施 .........................................................................................................................7
3.1 测量放样...............................................................................................................................................7
3.2 沟槽开挖...............................................................................................................................................7
3.3 基础垫层施工.......................................................................................................................................8
3.4 管道敷设...............................................................................................................................................9
3.5 管道包封...............................................................................................................................................9
![](https://csdnimg.cn/release/download_crawler_static/89293585/bg2.jpg)
3.6 人(手)孔井砌筑..............................................................................................................................10
3.7 沟槽回填.............................................................................................................................................10
第四章 质量保证措施 ...................................................................................................................................11
4.1 组织保证措施.....................................................................................................................................11
4.2 制度保证措施.....................................................................................................................................11
4.3 技术保证措施.....................................................................................................................................12
第五章 工期计划及保证措施 .......................................................................................................................12
5.1 工期计划.............................................................................................................................................12
5.2 工期保证措施.....................................................................................................................................13
第六章 安全、文明及其他保证措施 ...........................................................................................................13
6.1 安全生产保证措施..............................................................................................................................13
6.2 文明施工措施.....................................................................................................................................14
![](https://csdnimg.cn/release/download_crawler_static/89293585/bg3.jpg)
第一章 概 况
1.1 编制依据
1.1.1《通信管道工程施工及验收规范》(GB50374-2006);
1.1.2《通信管道横断面图集》(YD/T5162-2007);
1.1.3《通信管道人孔和手孔图集》(YD5178-2009);
1.1.4《通信管道人孔和管块组群图集》YDJ-101;
1.1.5《地下通信线路安装》(05X101-2);
1.1.6 文通路通信工程施工设计图纸。
1.2 工程概况
1.2.1 施工内容
文通路为新建道路工程,设计范围北起豫兴大道,南至郑开大道,全长 2044.158
米,文通路沿线分别与豫兴大道、郑开大道北辅道、郑开大道等 9 条东西向道路相
交,其中郑开大道为现状道路,郑开大道北辅道、祭城路为同期设计道路,其余均
为规划道路。文通路道路红线宽度 50m,规划为四幅路横断面形式。
本次设计通信线路全部采用电缆排管埋地敷设,本工程包含通信电缆排管及人
孔井;主干线采用 24 根排管(4 层×6),其中 16 根为 Ø110PVC 管,8 根为 7 孔
(7×Ø32)梅花管;过路支管预埋 8 根排管(2 层×4),其中 2 根 Ø110PVC 管,6 根
7 孔(7×Ø32)梅花管;管材选用 PVC 塑料管(硬聚氯乙烯管);预留支管位置可根
据道路两侧用户情况进行现场调整。
通信管线位于道路中西 22 米处,渠化段通信管线位于道路中西 25 米处;通
信电缆排管在人行道下最小覆土厚度为 0.7 米,车行道下最小覆土厚度为 0.8 米;
当覆土不满足要求时采用素混凝土包封。
通信人孔井中心位于道路中南 22 米处和 25 米处,电缆排管向人孔井侧排水坡
度不小于 0.3%,本次设计人(手)孔井均选用小号井,当人孔内部净高不大于 2.7
米时壁厚 240㎜,当净高大于 2.7 米且小于 4 米时壁厚 370㎜;道路交叉口之间、
![](https://csdnimg.cn/release/download_crawler_static/89293585/bg4.jpg)
道路过路工作井均位于距道路红线外 1 米米处,现场施工时可适当调整。
1.2.2 主要工程量
主要工程量一览表
序号
名称
规格型号
单位
数量
1
直通人孔井
小号
座
37
2
四通人孔井
小号
座
11
3
手孔井
小号
座
5
4
电缆排管
24 根(8*Φ110PVC+16 根 7 孔梅花管)
米
2250
5
电缆排管
12 根(4*Φ110PVC+8 根 7 孔梅花管)
米
440
6
电缆排管
8 根(2*Φ110PVC+6 根 7 孔梅花管)
米
180
第二章 施工安排
2.1 前期准备
施工前充分做好各项准备工作,包括控制测量工作;原材料检验,砂浆、砼配
合比设计;钢筋加工场地的建设;施工用水;电力供应;道路交通疏导;管线调查;
施工材料等统筹安排;进场人员安全教育等确保满足施工需要。
2.2 人员组织
根据合同要求和总体施工计划,为顺利完成道路管线工程,我处组织具有丰富
施工和管理经验的工程技术人员担任项目主管和技术主管,并组织技术过硬、操作
熟练的现场技术人员进行施工业。计划投入施工人员计划 63 人:
主要人员配置表
![](https://csdnimg.cn/release/download_crawler_static/89293585/bg5.jpg)
2.3 技术准备
2.3.1、项目总工组织项目部工程技术人员,进一步熟悉施工图纸和设计文件,
了解并掌握设计意图,并对施工现场作进一步的实地察看,然后根据管线所处的位
置以及技术要求的不同来编制本专项施工方案,并上报监理工程师审核批准。
2.3.2、及时办理相关报验报批手续;
2.3.3、向参加施工的全体人员进行技术、安全等方面的交底。
2.4 主要设备配置
主要机械设备一览表
机械名称
型号
规格
数量(台)
挖掘机
PC220
1.0M
3
1
装载机
ZL50
3m
3
1
小型冲击夯
BS700
6
发电机
柴油机
30KW
2
钢筋切断机
WS40-1
4KW
1
钢筋弯曲机
WS-1
5KW
1
电焊机
BX6-350
24KW
2
序
号
人员配置
单
位
数
量
备注
序号
人员配置
单
位
数
量
备注
1
管理人员
人
8
6
电焊工
人
2
2
机手
人
2
7
钢筋工
人
5
3
木工
人
4
8
砌筑工
人
10
4
普工
人
12
9
管道工
人
10
5
测量工
人
4
10
砼工
人
6
剩余22页未读,继续阅读
资源评论
![avatar-default](https://csdnimg.cn/release/downloadcmsfe/public/img/lazyLogo2.1882d7f4.png)
![avatar](https://profile-avatar.csdnimg.cn/a98d4288f72742afbab41a0d2b2e653c_m0_38073539.jpg!1)
平头哥在等你
- 粉丝: 3
- 资源: 7333
上传资源 快速赚钱
我的内容管理 展开
我的资源 快来上传第一个资源
我的收益
登录查看自己的收益我的积分 登录查看自己的积分
我的C币 登录后查看C币余额
我的收藏
我的下载
下载帮助
![voice](https://csdnimg.cn/release/downloadcmsfe/public/img/voice.245cc511.png)
![center-task](https://csdnimg.cn/release/downloadcmsfe/public/img/center-task.c2eda91a.png)
安全验证
文档复制为VIP权益,开通VIP直接复制
![dialog-icon](https://csdnimg.cn/release/downloadcmsfe/public/img/green-success.6a4acb44.png)