目录
一、工程概况 ···································································2
二、编制依据· ···································································2
三、降水方案选择·······························································2
四、井点降水相关计算·························································3
五、主要降水设备·······························································6
六、施工工期·····································································7
七、井点施工方法·······························································7
八、质量标准及质量保证措施················································8
九、危险点分析································································10
十、安全生产及文明施工措施···············································10
十一、环保措施································································11
一、
工程概况
本期设计为2×600MW亚临界汽轮发电机组。
工程地质情况:本工程持力层采用③圆砾层做持力层,③圆砾,层顶一般埋深3.0m ~4.5m,一般厚度6.5m ~9.5m。④细中砂层,层顶埋深一般为10.0m ~13.0m。一般厚度5.0m~7.0m。⑤圆砾层分布于④层之下。层顶一般埋深15.0m ~18.0m。⑥粘土(残积土),褐色,稍湿,坚硬,覆于凝灰岩之上。最大厚度大于6.8m。
二、编制依据
《火电施工质量检验及评定标准》
《电力建设施工及验收技术规范》
《建筑施工计算手册》
临时土方开挖图纸
三、降水方案选择
该项目地处伊敏河畔,属砂砾地质结构,渗透系数为150m/天,容水量大,受降水影响地下水位波动变幅1-2m 。枯水期在-6m左右。而本工程大部分建筑物埋深在-6m,处于临界状态,丰水期就无法施工,本工程采取的措施是:采用明沟、集水井的方式进行作业层表面水的降水。在枯水期柱、基础底脚施工完、回填完,防止丰水期淹没,以减少降水施工的降水费用。基础埋深超过-6m的,采用局部井点降水。
本工程主厂房基础底标高为-5.0m,不须采用井点降水,而循环水泵坑及汽轮机基础底标高为-7.5m,可采用轻型井点降水。基础平面基底长度约为50m,宽度约为36m。基础埋深为见施工图,地面持力层为圆砾层,井点降水可以避免大量涌水、冒泥、翻浆,而且在砂砾地层中开挖基坑时,可防止流砂现象发生,渗流向下改善土的性质,使基底土质更加密实,结合本工程基础施工主要在枯水期期间,周期较长的特点,采用轻型井点降水法,沿建筑物环状布置进行人工降水。同时基坑二角设集水箱配合4台QY-3.5型潜水泵排除明水的方法。
四、井点降水相关计算
1、井点管的埋设深度
H≥H1+h+iL+l
式中 H——井点管的埋设深度(m)
H1——井点埋设面至基坑底面距离(m) 取3.0m
h—— 基坑中央最深挖掘面至降水曲线点的安全距离(m)取1.0m
L—— 井点管中心至基坑中心的短边距离(m) 取27
i—— 降水曲线坡度 取1/10
l—— 滤管长度(m)取1.2
H≥3.0+1.0+27×1/10+1.2=7.9m 取8m
2、涌水量计算
Q=1.366K
Q——井点系统总涌水量(m3/d)
K——渗透系数(m/d)取150
H——含水层厚度(m)计算暂取11m
R——抽水影响半径(m)计算取91
S——水位降低值(m)取1.2,地下水位取6.8m
【轻型井点降水方案】
本方案针对2×600MW亚临界汽轮发电机组建设中的地下水处理,尤其适用于工程地质条件复杂、渗透系数较高的砂砾地质结构。项目地点位于伊敏河畔,其渗透系数为150m/天,地下水位在枯水期大约在-6m,但在丰水期会升高,这对施工带来挑战。由于大部分建筑物的埋深接近地下水位,因此需要采取有效的降水措施以确保施工安全。
根据工程概况,持力层由③圆砾层构成,埋深3.0m~4.5m,厚度6.5m~9.5m;紧接着是④细中砂层,埋深10.0m~13.0m,厚度5.0m~7.0m;再往下是⑤圆砾层,埋深15.0m~18.0m。在这样的地质条件下,采用明沟、集水井结合局部轻型井点降水的策略。对于基础埋深不超过-6m的部分,主要通过明沟和集水井排除表面水;而对于基础埋深超过-6m的循环水泵坑和汽轮机基础,则采用轻型井点降水,以防止流砂现象和改善土质。
在计算井点管的埋设深度时,依据了H1(井点埋设面至基坑底面距离)、h(安全距离)、L(井点管中心至基坑中心的短边距离)、i(降水曲线坡度)和l(滤管长度)。根据给定数据,计算得出井点管的埋设深度至少为7.9m,实际取8m。
涌水量的计算涉及渗透系数K、含水层厚度H、抽水影响半径R、水位降低值S等因素。采用无压非完整井计算公式,考虑到工程的具体参数,最终得出总涌水量为8818m³/d。
在确定井点管的数量和间距时,需要考虑单井出水量q,该值与井点管直径d和长度l以及渗透系数K有关。同时,井点布置应沿建筑物环状分布,以达到最佳降水效果。基坑的集水箱配合潜水泵用于排除明水,确保施工区域的干燥。
施工工期、井点施工方法、质量标准及质量保证措施、危险点分析、安全生产及文明施工措施、环保措施等章节则详细规定了施工过程中各个阶段的具体操作、控制标准、安全防范和环境保护等方面的要求,确保工程的顺利进行且对周边环境影响最小。
轻型井点降水方案是根据工程地质特性、地下水位变化以及施工需求综合制定的,旨在确保2×600MW亚临界汽轮发电机组的基础施工能够在地下水得到有效控制的情况下安全、高效地完成。通过科学的计算和合理的布局,方案兼顾了施工效率和环境保护,为大型电力工程的地下水管理提供了有效参考。