Answer: A,C,D
QUESTION NO: 18
When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula
parameters for calculation. What can be the origin of the formula parameters used for scheduling?
(Choose three.)
A. General values from work scheduling view in the material master
B. Standard value from operation in task list
C. User-defined field from operation in task list
D. General operation values in task list
E. General item values in bill of materials
Answer: B,C,D
QUESTION NO: 19
A user has entered planning strategy group 10 (make-to-stock production) in the material master (SAP
ECC) of a product. For the coming months, requirements with requirement type LSF (derived from the
main strategy 10) have been planned. The user would like to change the requirement type from LSF to
VSF planning with final assembly (in accordance with planning strategy 40) for requirements in the
production plan that have already been saved.
Which of the following statements are applicable in this case? (Choose two.)
A. The user has to change the requirement type for planning strategy 10 to VSF planning with final
assembly in Customizing. The requirement type for all existing requirements is then changed
automatically.
B. The present requirement for the product can be changed manually from LSF to VSF in the
Requirement Type field in the production plan, so that the new strategy 40 determines the next planning
operation.
C. The user can enter the new planning strategy group 40 in the material master of the product, but the
requirement type is not changed automatically for existing requirements.
D. The planning strategy group can be changed from 10 to 40 in the existing production plan, and the
requirement type for all requirements is changed automatically.
Answer: B,C
QUESTION NO: 20
Which of the following statements about the planning functions available in SAP ECC are true?
(Choose two.)
A. Master production scheduling (MPS) refers to preferred planning of important materials.
B. Material requirements planning (MRP) does not include automatic capacity leveling.
C. Long-term planning (LTP) is a long-term form of forecast planning.
D. In demand management (DM) material shortage situations are identified and given requirement
coverage elements.
Answer: A,B
QUESTION NO: 21
Which data forms the basis for calculating the capacity requirement for an operation?